Method of installation of the screen machine
The air curtain machine is installed at the door of the shopping malls, theaters, hotels, restaurants, conference halls, refrigerators, operating rooms and home furnishings such as refrigeration, air conditioning, dustproof, and heat insulation.Strong airflow form an invisible curtain.So what are the installation methods and precautions for the curtain machine?
1. The wind curtain machine should be installed on the door frame
2. The width of the door must be less than or equal to the length of the wind curtain; (if the door hole is too width, connect several curtain machines to install and use).
3. Installing the bottom plate must be firmly connected to the wall (or on the pillars) to prevent vibration caused by looseness.
Method of installing the bottom plate:
Installed on the concrete wall, according to the position of the hole on the bottom plate, arrange the relative size position of 8 bolts 10 × 60, and embed the bolt in the cement.Then fix the installation bottom plate.Or flush directly on the concrete wall and fix it with expansion screws.
1. After the mulch is fully fixed, fix the bundle of the installation board on the bolt.8 bolts are fixed on the concrete wall or door frame.
2. The body hanging corner must be inserted into the installation plate and install the hole.
3. Remove the screw of the panel after the off -air curtain machine, remove the hanging board;
4. Put the hanging board firmly on the installation position;
5. The air outlet is poured down on the fixed hanging plate at the down;
6. Tighten it with the removed screws.
Precautions for installation of the screen machine
1. Before installing the air curtain machine, the professional must calculate the capacity of the power supply and the cross area of ??the wire, and ensure that the wire of the power supply meets the requirements of the weather curtain.
2. There must be no one below the machine when installing the machine. The current capacity of the natural wind machine installation of the power socket should be above 10A.public.
3. If the door is wider than the installation of the air curtain machine, it can be installed with two or multi-typhoon curtain machine combinations. In this case, the two wind curtain machines can be kept better at 10-30mm between the two wind curtain machines.
4. Please do not install the wind curtain in places where it is easy to splash water and long -term exposure to high temperature or toxic gases, and corrosive gases.
5. Electric heating air curtain machine is high.N is a zero line, L1, L2, and L3 are fire lines. The yellow -green two -color line is the ground line. You can choose different power to determine different temperatures.The 220V wiring can only connect the N and L1 red wires. The 380V wiring can be connected at the same time with the L1, L2, and L3. The wiring should be firm and loose.